Question No. 1. Which one of the following represents an activity:
A. excavation for foundation
B. curing of concrete
C. setting of question paper
D. preparation of breakfast
E. all the above.

 

 

Question No. 2. Pick up the incorrect statement from the following:
A. An activity of a project is denoted by an arrow on the net work
B. The tail of the arrow indicates the start of the activity
C. The head of the arrow indicates the end of the activity
D. The arrows are drawn to

 

 

Question No. 3. The technique for establishing and maintaining priorities among the various jobs of a project, is known:
A. Event flow scheduling technique
B. Critical ratio scheduling
C. Slotting technique for scheduling
D. Short interval scheduling.

 

 

Question No. 4. Mile Stone charts were invented in the year of:
A. 1910
B. 1920
C. 1930
D. 1940
E. 1950

 

 

Question No. 5. Frederick W. Taylor introduced a system of working known as:
A. line organisation
B. line and staff organisation
C. functional organisation
D. effective organisation.

 