Question No 1: Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds…
A: 2.0%
B: 2.5%
C: 4.0%
D: 5.0%
Question No 2: The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is….
A: 1.00 m3
B: 1.25 m3
C: 1.50 m3
D: 1.75 m3
Question No 3: The following item of earth work is not measured separately…
A: Setting out of works
B: Site clearance
C: Dead men
D: Steps in deep excavation
E: All of the above
Question No 4: Pick up the correct statement from the following….
A: The incidental expenses of a miscellaneous character with could not be predicted during preparation of the estimate, is called contingencies.
B: Additional supervising staff engaged at work site, is called work charged establishment.
C: Detailed specifications specify qualities, quantities and the proportions of materials to be used for a particular item.
D: The cost per unit at which the article can be procured, from the open market at a given time, is called ‘market rate’.
E: All of the above
Question No 5: Pick up the correct statement from the following:
A: In order to check up the average depth of excavation, ‘Dead mans’ are left at the mid-widths of borrow pits.
B: The earthwork calculation in excavation is made from the difference in levels obtained with a level.
C: The earth work in excavation to form the road embankment includes the formation of correct profile and depositing the soil in layers.
D: All the above
Question No 6: The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chain age is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by prismoidal formula, is….
A: 3250 m3
B: 3225 m3
C: 3275 m3
D: 3300 m3
Question No 7: The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended….
A: 100 mm
B: 150 mm
C: 200 mm
D: 175 mm
Question No 8: Pick up the correct statement from the following….
A: Bricks are paid per thousand
B: Cement is paid per 50 kg bag
C: Lime is paid per quintal
D: Brick aggregates is paid per cum
E: All of the above
Question No 9: The weight of an item is measured correct to nearest….
A: 0.25 kg
B: 0.50 kg
C: 0.75 kg
D: 1.00 kg
E: 5.00 kg
Question No 10: The rate of payment is made for 100 cu m (per % cu m) in case of….
A: Earth work in excavation
B: Rock cutting
C: Excavation in trenches for foundation
D: Earth work in filling the plinth
E: All of the above
Question No 11: The measurement is made in square meter in case of….
A: Cement concrete in foundation
B: R.C.C. structure
C: Hollow concrete block wall
D: Concrete fencing posts
E: None of these
Question No 12: Berms are provided in canals if these are….
A: Fully in excavation
B: Partly in excavation are partly in embankment
C: Fully in embankment
D: All of the above
Question No 13: The brick work is not measured in cu m in case of….
A: One or more than one brick wall
B: Brick work in arches
C: Reinforced brick work
D: Half brick wall
Question No 14: The rate of an item of work depends on….
A: Specifications of works
B: Specifications of materials
C: Proportion of mortar
D: Method of construction
E: All of the above
Question No 15: Pick up the correct statement from the following….
A: All pipes and fittings are classified according to their diameters
B: The diameter of the pipes is the nominal diameter of internal bore
C: All pipes are measured along the centre line of the pipes in meters
D: Lead caulked joints are enumerated separately
E: All of the above
Answers Here
- D
- B
- E
- E
- D
- B
- B
- E
- D
- E
- E
- B
- D
- E
- E